Hi Oracle gurus,

I have a scenario where Internal requisition has the need by date same as requisition's creation date ,but have been approved next day.

Now when the Sales Order is created , schedule dates are blank and u cant even update them. Sales order has to be cancelled and new requisition has to be created.

Can you pls suggest some alternative solution for this...

Thanks & Regds
Rekha
rajaryanreddy
Posts: 23
Joined: Wed Sep 12, 2007 3:35 am
Location: India
Contact:

Post by rajaryanreddy »

I think we need to change the setup.The scheduled date on sales order not to be populated from need by date on requistion .
or
Alternatively when need by date is entered on requistion make a constraint that it should be approved before need by date .If it is not approved by need by date the requistion should be disqualified or after it is approved by the need by date there should be feasibility to change the need by date on requistion .