Hi
I am having Oracle MS/MRP and Oracle ASCP.
I want to manufacture item as PEN. All accessories for PEN are buy items
Please let me how MS/MRP & ASCP will work to manufacture a pen.
What are the setup differences for the same of these 2 modules?
Thanks,
PJ
Manufacturing flow of MS/MRP and ASCP
-
- Posts: 7
- Joined: Thu Jul 09, 2009 3:54 am
- Location: India
Hi,
Using both you can do planning for mfg.
For MS/MRP you have to setup organization parameters and item attribute (General planning & MPS/MRP Planning tab)
For ASCP you have to crate plan instance seperatley and many other setup you have to do, which need more effort than MS/MRP. Please follow ASCP user guide.
ASCP is more efficient than MS/MRP. But it will take longer time for data collection and plan running.
If Data volume is bulk then for ASCP Seperate Plan instance may required. (Seperate plan server)
Regard
Using both you can do planning for mfg.
For MS/MRP you have to setup organization parameters and item attribute (General planning & MPS/MRP Planning tab)
For ASCP you have to crate plan instance seperatley and many other setup you have to do, which need more effort than MS/MRP. Please follow ASCP user guide.
ASCP is more efficient than MS/MRP. But it will take longer time for data collection and plan running.
If Data volume is bulk then for ASCP Seperate Plan instance may required. (Seperate plan server)
Regard