I create Discrete Job with quantity 40000 then I complete 1000, If I complete and the closed the job that stage, what wi

Here members can post Oracle Manufacturing related questions and answers.
Post Reply
tariqbashir
Posts: 10
Joined: Mon Dec 04, 2006 12:20 pm
Location: Saudi Arabia

I create Discrete Job with quantity 40000 then I complete 1000, If I complete and the closed the job that stage, what wi

Post by tariqbashir »

I create Discrete Job with quantity 40000 then I complete 1000, If I complete and the closed the job that stage, what will be the effect, how cost will be calculated.
Regards
Tariq Bashir