Hi
Check whether that recipe validity rule has that Inventory organization assigned to it.
Also make sure that the items in the formula are assigned to that Inv org
Regards
Ramesh
Search found 5 matches
- Mon Sep 21, 2009 7:47 am
- Forum: Manufacturing
- Topic: Document creation
- Replies: 2
- Views: 3974
- Fri Feb 06, 2009 5:57 am
- Forum: Manufacturing
- Topic: Material Requirement Planning Exception detail
- Replies: 5
- Views: 5455
Hi Can anyone please explain what 'Late Replenishment of forecast mean? Actually Im using ASCP with OPM and running an ECC plan. I gave a forecast say on 1st Apr but the plan is giving an output as demand on 3 may instead of 1st Apr and in the exception details, we get Late repelnishment of forecast...
- Sat Jan 24, 2009 3:57 am
- Forum: Manufacturing
- Topic: OPM Financial
- Replies: 3
- Views: 2991
Hi In OPM the costing can only happen if you run the Actual cost process. As a general rule a period in OPM is 1 month and at the end of the month when all the transactions are complete, you need to run the ACP, and cost update so that the cost is correctly calculated. However if you need daily cost...
- Sat Jan 24, 2009 3:18 am
- Forum: Manufacturing
- Topic: Forecast Consumption is done for DropShip SO ?
- Replies: 1
- Views: 1420
- Sat Jan 24, 2009 3:12 am
- Forum: Manufacturing
- Topic: Manufacturing document
- Replies: 3
- Views: 3361