Q in Inventory+ Purchase Requsition

Posted: Wed Aug 30, 2006 9:38 am
by coffee
SalaM,

If I Use the min-max planning method, and when a Min Quantity reached, how can I let the system automatically place a purchase Requsition to buy the needed Qty ??

Thanx.

Posted: Thu Aug 31, 2006 8:58 am
by admin
You will have to submit request "Min-max planning report" or schedule it. Hope it will work for you. thanks

Posted: Mon Sep 04, 2006 4:01 am
by Ahsan
Dear, When you have run the Min-Max report then you should import. then you will be able to see the created requisition, and then will be make from it Release or Pos.