Funds Check Level

Posted: Mon Jan 07, 2008 11:49 am
by h3am
The funds check level for all budget orgnaizations are None for 2007 Budget and we did not closed the 2007 year and we decided to start enter transctions in for 2008 year before close 2007 year but we need to change the check level for all budget organizations to Advisory or Absolute can any one tell me how I will handle this issue .

Thank
Hesham

Posted: Tue Jan 08, 2008 2:34 am
by anusha_rao
hi
if you have to change at the budgetary control ,it is easy.
query the category and source and change the funds check level
regards
rao
apps consultant
chennai

Posted: Tue Jan 08, 2008 4:19 am
by h3am
Thanks rao.
But I did not use the budgetry control group.

1- I have budget organization have none fund check levels
2- 2007 year transactions not finished
3- Need to change the Funds Check level for this budget organization for 2008 and not effect in 2007

Thanks and please any one try to help me

Hesham

Posted: Tue Jan 08, 2008 10:06 am
by anusha_rao
hi
just go through the following steps
1)if you have given none at the organisation level,you can override by changing at the budgetary control option.
2)if you gave absolute at the organisation level it wil take precedence.
3)in you case you can change to either absolute or advisory in the budgetary control group.
4)check the profile option for budgetary control group
any clarification kindly get back to me
regards
rao