AP Payment Terms

This forum is to discuss different features/issues of Oracle Financials modules ( GL - General Ledger, AP - Accounts Payable, AR - Accounts Receivable, FA - Fixed Assets & CM - Cash Management ).
Post Reply
aanchan_001
Posts: 4
Joined: Mon Jul 16, 2007 10:36 am
Location: India

AP Payment Terms

Post by aanchan_001 »

Hi We have some payment terms to be set in AP, can someone help me on this

1.25% advance with PO, 35% on completion of delivery at site, 30% on virtual completion balance 10% (after successful installation) against the unconditional performance Bank guarantee of 10% of total purchase order value valid for 12 months from the date of delivery

2. 50% against delivery of material at site and acceptance/approval of our Engg Dept. 45% against completion of work, site-wise and against approval of our Engineering Dept. 5% after 3-months from date of handing over of site to us.

3. 95% against running bills duly certified from our Engineering Dept. 5% to be paid after 12 months from the date of completion of Civil work & acceptance/approval of our Engineering dept.

Mohan
hiszaki
Posts: 482
Joined: Thu May 10, 2007 9:03 am
Location: Egypt

Post by hiszaki »

Hi Mohan

I would like to ask you, the time between each process (like delivery at site, completion of work, ...) is a different or a fixed time?

If the time are fixed then you can handle the payment terms according to your time.

Thanks
Hisham