Hi!
Can anyone help me with minmax planning. I have an item which is a raw material (item A) for a finished good item(item B). I have an open Sales Order for item B. However when i run the minmax planning report, item A does not include the quantity supposedly on the sales order for item B. How do I check on this?
raja_rthiyagu
Posts: 53
Joined: Tue May 29, 2007 6:07 am
Location: USA

Post by raja_rthiyagu »

hi,

Have you created Bom and Routing for Item B .
Arshadimrany
Posts: 32
Joined: Thu Dec 21, 2006 2:20 am
Location: India

Post by Arshadimrany »

I dont think we can run Mix Max planning.... But iam not sure. I feel it is related to MRP Planning.

Please correct me if iam wrong.
Nevada
Posts: 2
Joined: Wed May 23, 2007 7:20 am
Location: Philippines

Post by Nevada »

We have defined BOM and routing. In fact we even have discrete jobs already. But how true is it that if the discrete job is not released, then the demand in the SO will not be included in the min/max planning?
raja_rthiyagu
Posts: 53
Joined: Tue May 29, 2007 6:07 am
Location: USA

Post by raja_rthiyagu »

hi,

i thought its not possible to utilize SO demand in Min-Max , we can perform this through MRP