Page 1 of 1

Purchase Requisitions

Posted: Fri Jun 08, 2007 3:46 am
by anu_uma
Hi All,

Is it possible to enter a Purchase requisition on a Date earlier than the current date?? if Yes what is the step to enable the back date?


TIA

Posted: Sun Jun 10, 2007 1:24 am
by SIVAKUMAR_G
Hi

From PO User guide

Enter the Need By date for the requested items. This is required only for planned items. You must enter a date greater than or equal to the requisition creation date.

You want to creation date back dated or Need by Date Back dated?

Regards
Sivakumar

Posted: Tue Jun 12, 2007 8:37 am
by anu_uma
Hi Siva,

Ur Replies are interesting...

here I need both the dates to be back dated ? what is the procedure to do it so?


TIA

Posted: Wed Jun 13, 2007 3:12 pm
by arun1203
Hi Uma,

Your question is bit vague.
Let me explain you what I've understood from your question.

<font color="red"><b>You are trying to create a Purchase Requistion with a need by date which is earlier than the current date?</b></font id="red">

This is not possible. Always the need by date should be greater than or equal to creation date.

And according to me you cannot back date the requistions creation date.
Means let us say you are creating a requistion on 13th July 2007 but you want it to be 12th july 2007 which is not possible according to me.

Anyway let us wait for the members if any of them has a way to back date it.

<font color="blue"><i><b>Best Regards & Thanks,
Arun Reddy</b></i></font id="blue">[:)]