Cann't copy a Budget in PA

Posted: Fri Sep 12, 2008 5:39 am
by dvsprao108
hi friends,

when i want to create a new project by using the previous project as a tamplate, its throughing an error message as below.
"Cannot copy a budget to a period which is out of the range of system define periods" (example: PA period to GL period).

Can anyone please tell me how to overcome the above problem?

thanx,
dvsprao108@gmail.com

Posted: Fri Sep 12, 2008 5:50 am
by cbalakri
Can you check the start date and end date of the project you are trying to create. Check the budget dates of the source project as well. Hope, this gives you the answer.