Move Order approval Process
Posted: Mon Apr 27, 2009 8:57 am
by phani
Hi all,
When we raise move order, is there any way that the move order follows the Emp/Supervisor Hierarcy (i.e., what we follow in Purchasing).
Thanks in Advance.
Regards,
Phanindra
Posted: Mon Apr 27, 2009 10:34 am
by imtiyaz
Dear
Do the following steps
1. Move Order Timeout Period : 0 Days - Organization Parameters
2. Go to Inventory->Setup->Planners ? Define planner
3. Go to Item Master on the Item level define at General Planning : Assign Planner
Note: You can?t define approval Hierarchy key like in Purchase Request or Purchase Order
In move order one step approval.
Hope this will be solve your problem
Regards
Posted: Wed Apr 29, 2009 9:34 am
by phani
Hi,
In the way you have mentioned move order will go to the planner of the item for approval. But my requirement is it should go to the supervisor of the particular employee.
Thanks and regards
Posted: Thu Apr 30, 2009 2:49 am
by imtiyaz
Hi
Not possiable via Move order. In that case you use IRO to map the same bussiness process. (Internal Requisition Process, where you can build employee supervisor Approval Hierarchy.
Pls. let me know it you have help to map this process.
Regards
Posted: Mon May 04, 2009 6:55 am
by phani
Hi Imtiyaz,
Could you please let me know how Internal Requisitio Process is used to map this process.
thanks in advance
Regards,
Phani
Posted: Tue May 12, 2009 4:31 am
by phani
Hi Imtiyaz,
Could please spare some time of yours to help me out
Thanks and regards,
Phani
Posted: Wed May 13, 2009 9:10 am
by imtiyaz
Hi,
I try couple of time to upload a file (setup documents) without sucess.
Hi Admin,
Please help to upload the file.
Regards
Posted: Thu Feb 04, 2010 3:59 am
by admin