Page 1 of 1

Manufacturing flow of MS/MRP and ASCP

Posted: Thu Jul 09, 2009 8:19 am
by Pjain59882
Hi
I am having Oracle MS/MRP and Oracle ASCP.
I want to manufacture item as PEN. All accessories for PEN are buy items
Please let me how MS/MRP & ASCP will work to manufacture a pen.
What are the setup differences for the same of these 2 modules?

Thanks,
PJ

Posted: Thu Jul 16, 2009 10:01 am
by edmattu
Hi,
Using both you can do planning for mfg.

For MS/MRP you have to setup organization parameters and item attribute (General planning & MPS/MRP Planning tab)

For ASCP you have to crate plan instance seperatley and many other setup you have to do, which need more effort than MS/MRP. Please follow ASCP user guide.

ASCP is more efficient than MS/MRP. But it will take longer time for data collection and plan running.

If Data volume is bulk then for ASCP Seperate Plan instance may required. (Seperate plan server)

Regard

Posted: Tue Aug 18, 2009 6:30 am
by phani
Hi,

Please refer http://www.oracleug.com

Regards