How to change the Maturity date for a Payment?
Posted: Sat Oct 29, 2011 4:57 am
Hi,
I created Payment today (2011/10/29) with a Maturity date <b>2011/12/25</b> and issued the check to Supplier.
Now i want change the maturity date, because on the maturity date (2011/12/25) company does not have sufficient funds and need to change date to <b>2011/12/30.</b>
The Maturity date button is grade out and unable to change. Please let me know your valuable suggestions on this Issue.
Thanks & Regards,
Anjireddy
I created Payment today (2011/10/29) with a Maturity date <b>2011/12/25</b> and issued the check to Supplier.
Now i want change the maturity date, because on the maturity date (2011/12/25) company does not have sufficient funds and need to change date to <b>2011/12/30.</b>
The Maturity date button is grade out and unable to change. Please let me know your valuable suggestions on this Issue.
Thanks & Regards,
Anjireddy