Page 1 of 1

How to handle this type of Problem in Reports

Posted: Fri May 12, 2006 6:11 am
by RiazAhmad
I have the following Problem. the description with example is given below
Suppose u have 15 pieces. and u want to plan these 15 pieces within 6 six days equaly.But when u do it u have the following problem.
without rounded rounded
Qty 1 2.5 3
Qty 2 2.5 3
Qty 3 2.5 3
Qty 4 2.5 3
Qty 5 2.5 3
Qty 6 2.5 3
Total 15 18
So i dont want to display figures with decimal points. but in this case i got 18 total while the actual was 15;
Thanks,
Regards,

Riaz Ahmad

Posted: Fri May 12, 2006 6:21 am
by admin
Pl don't consider it that you have to do it or doing with Oracle reports first do it manually on the paper and if it is possible then do let us know. As reports will also calculate on the basis of data provided. thanks